Details
-
Bug
-
Resolution: Fixed
-
High
-
3.10.2
-
3.1
-
Description
Moving Problem when changing Project, IssueType and Sub-IssueType
Issue Type Configuration
- Issue Type Scheme ITS_A with
- Issue Type IT_A
- SubTask IT_B
- Issue Type Scheme ITS_B with
- Issue Type IT_C
- SubTask IT_D
Project Settings
- Project A with Issue Type Scheme ITS_A
- Project B with Issue Type Scheme ITS_B
Issue to move
Project A contains :
- an Issue IA typed IT_A with a Sub-Task IB type IT_B
When I init a move of Issue IA from projet A to Project B, the Wizard ask :
- At step 1 : the target Project (here Project B) and then the Issue Type (here IT_C)
- At step 2 : the target status for Issue IA and sub-Task IB, but proposed status for sub-Task are issued from jira workflow and not the Workflow defined for the SubTask IT_D
Hopping that my explanation is correct.
V.