Use advancement percentage in addition of the time remaining

XMLWordPrintable

      NOTE: This suggestion is for JIRA Cloud. Using JIRA Server? See the corresponding suggestion.

      It would be great to add the issue field advancement percentage for time tracking. This field could be updated in concert with the remaining estimate and time spent. For example, a task with 4 days of time spent and 6 days of remaining estimate may have an advancement percentage of 40%
      (time spent / (time spent + remaining estimate)).
      Also when logging work it may be used to adjust estimate. A developper could state that he's at 75% of advancement. For example,
      Original estimate 4d
      time spent: 2d (developper entry)
      advancement %: 75% (developper entry)
      With those entries, Jira could adjust the remaining time to 5.3 hours
      (time spent / advancement percentage - time spent)

      I propose that because our administrator like % and for them it's easier to see the overall advancement with % instead of time.