Importing an XML Export does not create inline tasks and comments correctly

XMLWordPrintable

    • 28
    • Severity 2 - Major
    • 1

      NOTE: This bug report is for Confluence Cloud. Using Confluence Server? See the corresponding bug report.

      Steps to Reproduce
      1. Create a new Space
      2. Export the Space as XML
      3. Delete the Space you just created
      4. Import the Space Export
      5. On a page, create the Task Report Macro, and point it at the imported space.
      Expected Result

      The Task Report Macro should show the tasks that are incomplete, or complete (depending on the settings). Using this example, the report should show 4 incomplete tasks (from the default home page)

      Actual Result

      The Task Report Macro doesn't show the tasks that are incomplete. Marking a task as complete and then incomplete doesn't show the task either.

      The task does not appear in the database.

      Workaround

      None so far.