Suggestion
-
Resolution: Answered
-
None
-
None
NOTE: This suggestion is for JIRA Software Server. Using JIRA Software Cloud? See the corresponding suggestion.
Since I can edit the "Original Estimate" field of each story/subtask any time during the sprint (like when estimating was done on story cards, and I'm entering the estimates the day after start of sprint), I would expect the sprint start endpoint of the guidline to reflect the total of all "Original Estimate" fields' CURRENT VALUES (not shouting; just emphasizing).
I just started a 90 point sprint, entering most estimates on day 2, but my guideline says it's a 2 point sprint, so it's useless.
(I disagree with other users who want the guidline to be the guideline for work remianing. I want to know where my original estimate guideline is, so I know how far off plan discovery has driven me, so I can adapt the depth of my work and my plan to hit the end date.)
Thanks! Great tool!
- is related to
-
JSWSERVER-2511 Guideline on hour burndown chart uses original estimates not remaining estimates
-
- Closed
-
-
JSWSERVER-1864 Use (only) version start / end dates for chartboard "guideline" end points
- Closed
- relates to
-
JSWCLOUD-4417 Guideline end point at Version Start Date should respect corrections made to "Original Estimate" field.
- Closed
-
JSWSERVER-1288 As a project manager, I would like to be able to view a burndown chart that clearly communicates changes in scope.
- Closed
This issue will not be addressed as it is related to Classic boards, which are no longer being improved and will be removed in the future. We encourage you to migrate to the new Agile boards for all future work.
Regards,
GreenHopper Team