Velocity Chart should show all Sprints and not be limited to last 7 Sprints

    XMLWordPrintable

Details

    • 709
    • 9
    • Our product teams collect and evaluate feedback from a number of different sources. To learn more about how we use customer feedback in the planning process, check out our new feature policy.

    Description

      Currently the Velocity Chart is hardcoded to show (max) last 7 sprints. Looking at the average amount of work completed in a sprint is the main value of the Velocity Chart, so the value of the Velocity Chart increases with every sprint, because the average is getting better.

      If you have Sprint of two weeks length, you are talking about only 3-4 months. If vacation or christmas time is in between, you average is getting poor.

      Therefore the limitation to show only last 7 sprints is bad and should be removed.

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              69595d4e90f7 Holger Schimanski
              Votes:
              617 Vote for this issue
              Watchers:
              292 Start watching this issue

              Dates

                Created:
                Updated: