Dependent issues should not allow overlapping dates when value is manually set in the plan

XMLWordPrintable

    • Icon: Suggestion Suggestion
    • Resolution: Unresolved
    • Plans - Timeline
    • None
    • 6
    • 2
    • Our product teams collect and evaluate feedback from a number of different sources. To learn more about how we use customer feedback in the planning process, check out our new feature policy.

      Problem Statement

      Currently, Jira allows user to overlap dates (Start Date / End Date) even when issues are dependent between each other.

      Expected Results

      A warning message should be shown. By now, a warning message is only shown in Dependencies Report and in Timeline the badge will turn red to indicate that the dates of this dependency don’t line up.

      Actual Results

      The overlapping of dates are not blocked. The setting of sequential / concurrent is only directly considered if you use Auto-Schedule feature.