Auto scheduling doesn't return correct results for time-based estimations with planned capacities

    XMLWordPrintable

Details

    Description

      Issue Summary

      Auto-scheduling doesn't return correct calculation results for time based estimations with planned capacities

      Steps to Reproduce

      1. Configure a plan to use time-based planning unit (days or hours)
      2. Create a few issues with estimations, for example 20 hours
      3. Update the planned capacities for a couple of future sprints, for example 40 hours (the default is 200 hours for 2 weeks)
      4. Run auto-scheduling

      Expected Results

      Planned capacities are considered by auto-scheduling and issues are pushed to further sprints when there is no enough capacity in current sprint

      Actual Results

      Issues are scheduled into the same sprint and allocated time exceeds the sprint capacity

      Workaround

      Currently there is no known workaround for this behavior. A workaround will be added here when available

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              08904538c6b6 Dong
              Votes:
              2 Vote for this issue
              Watchers:
              3 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved: