Unestimated child issues causes incoherent dependency scheduling

XMLWordPrintable

    • Type: Bug
    • Resolution: Not a bug
    • Priority: Low
    • Component/s: Plans - Timeline
    • None
    • 14
    • Severity 3 - Minor
    • 1

      Issue Summary

      When using the Auto-scheduler, unestimated issues under the parent causes it to propose incoherent dates that ignore the dependencies and creates conflict. This is also applicable when estimating with "0".

      Steps to Reproduce

      1. Create Task1, Task2 with 2 Subtasks and Task3
      2. Add the dependencies with Task3 blocking Task2 and Task2 blocking Task1
      3. Add an Estimate value to Task1, Task2 and Task3 (excluding the subtasks)
      4. Add the start/end dates to each Task making sure that they do not clash

      Expected Results

      When using the Auto-schedule, the scheduler is expected to provide new start/end dates taken into account the dependencies of the Tasks.

      Actual Results

      The scheduler completely ignores the dependencies and schedule dates that create depedencyes conflict with lead time.

      Workaround

      There are three possible workarounds:

      1. Give all child issues an estimate OR;
      2. Remove dates from child issues prior to autoscheduling OR;
      3. Selectively schedule the issues without their children by selecting them using the checkboxes before autoscheduling. This can be done more easily by using the hierarchy level filter to filter out issues on the child level before selecting all relevant issues to be scheduled.

      In cases 2 and 3, the child issues should then be manually scheduled after the autoschedule results are accepted.