As an Advanced Roadmaps user, I want to be able to baseline a plan against target dates

    • 94
    • 3
    • Our product teams collect and evaluate feedback from a number of different sources. To learn more about how we use customer feedback in the planning process, check out our new feature policy.

      As described in the documentation Adding target dates, the live plans (or the old version of Portfolio) allows users to baseline a plan against target dates, and this feature isn't present in Advanced Roadmaps.

      Suggested resolution

      As an Advanced Roadmaps user, I want to be able to store an initial baseline to be able to compare at a future stage.

          Form Name

            [JRACLOUD-88013] As an Advanced Roadmaps user, I want to be able to baseline a plan against target dates

            Customers want this but we as Partner cannot deliver, please implement.

            Ari Raatikainen added a comment - Customers want this but we as Partner cannot deliver, please implement.

            +1 we need this, too in my company

            Baechler Tobias (LMB) added a comment - +1 we need this, too in my company

            Eric added a comment -

            +1 Critical feature for my organization as well.

            Eric added a comment - +1 Critical feature for my organization as well.

            +1 critical feature also for us

            Chabane Degdag added a comment - +1 critical feature also for us

            Jean-Philippe Clipffel added a comment - - edited

            +1. This is a critical feature.

            As of today I literally have to maintain two plans (one for the baseline dates and another for the effective dates), and then split my screen in two horizontal sections to properly display them. This feel hack-ish as best.

            Jean-Philippe Clipffel added a comment - - edited +1. This is a critical feature. As of today I literally have to maintain two plans (one for the baseline dates and another for the effective dates), and then split my screen in two horizontal sections to properly display them. This feel hack-ish as best.

            + 1 really needed! Compare graphically your current plan with your baseline.

            Ramon Torras added a comment - + 1 really needed! Compare graphically your current plan with your baseline.

            this is going to be a big plus for Advanced Roadmap, we have to do too much manual workaround in order to keep baseline (created custom fields to record initial dates) and change start and due date, after you start priorities change, you shift tasks, but not possible to visualise what you planned v.s. actual

            Erdal Kaplan added a comment - this is going to be a big plus for Advanced Roadmap, we have to do too much manual workaround in order to keep baseline (created custom fields to record initial dates) and change start and due date, after you start priorities change, you shift tasks, but not possible to visualise what you planned v.s. actual

            +1

            Renee Niewald added a comment - +1

            +1

            Danie Salim added a comment - +1

            +1 really needed.

            Giuseppe Arria added a comment - +1 really needed.