Details
-
Bug
-
Resolution: Won't Fix
-
Low
-
1
-
Severity 3 - Minor
-
Description
Summary
The Burndown chart report shows story points estimation as "0" if an "In progress" status is moved to the right-most column
Environment
Jira Software cloud
Steps to Reproduce
- In a Scrum board with estimation set to story points, create some stories
- Set estimation to the stories
- Create a sprint and add the stories to it
- Start the sprint
- Map one of the "In progress" statuses to the right-most column
- Access the Burndown chart
Expected Results
The Burndown chart shows the estimation values as it was defined on the issues
Actual Results
Burndown chart shows the estimation of the issues in the "In progress" status mapped to the right-most column as "0"
Screen Recording 2018-08-31 at 09.53 PM.mov
Notes
Workaround
- Move the "In progress" status to a different column