Details
-
Bug
-
Resolution: Fixed
-
Medium
-
None
-
None
-
None
Description
Steps to reproduce:
- Board has working days Mon-Fri
- Today is Friday
- Create sample scrum board
- Version 3.0 has 2 issues, both 5 points. Mark one of them as done.
- View the Version Report.
Adding Saturday as a working day makes the prediction happen correctly.
Debugging through the code, it seems that the "estimate per day" is calculated as 0.