Details
-
Bug
-
Resolution: Fixed
-
Medium
-
6.1
-
None
-
6.01
-
Description
Steps to Reproduce:
- Create a new scrum board with stories more than 50
- Have Story Points for all of them with decimal values (say 5.1)
- Create Sprint to include all these stories so that the values goes above 240
Expected Results:
- The correct sum of the estimates are shown in the Estimate field
Actual Results:
- The Estimate will start showing up wrong values (an extra 2000 gets added)