As a Jira DC Administrator I want to be able to run scheduled tasks at specific nodes

    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      Problem Definition

      In Jira datacenter when a task is scheduled it could be picked up by any node. So there is no task affinity to a specific node.

      There are cases when a small Jira instance can handle all web traffic and only some tasks require more resources (due to heave processing required only for that execution).
      That makes scaling of the environment hard, since it requires all nodes to be equal.

      Suggested Solution

      Able to dedicate resource extensive tasks to a non-user facing node aka task affinity.

      Workaround

      None.

            [JRASERVER-70447] As a Jira DC Administrator I want to be able to run scheduled tasks at specific nodes

            There are no comments yet on this issue.

              Unassigned Unassigned
              ayakovlev@atlassian.com Andriy Yakovlev [Atlassian]
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated: