Wrong estimated time when importing from CSV

    XMLWordPrintable

Details

    Description

      I import issues in my JIRA project via CSV, but the estimated time after the import is too big. For example, one issue imported with the field for estimated time = 259200 seconds (3 days) results in an estimated time = 1w 4d.

      Attachments

        Issue Links

          Activity

            People

              Unassigned Unassigned
              0c88707c95ce Florina Craciunescu
              Votes:
              1 Vote for this issue
              Watchers:
              6 Start watching this issue

              Dates

                Created:
                Updated: