Issue Summary
Currently in advanced roadmap plans One team can have only one capacity and sprint length, since Tool doesnot offer flexibility include or exclude holiday and leaves for the team. It would be helpful to have more than 1 capacity defined to each team.
Steps to Reproduce
Go to plan settings > Teams > Create a team or use existing one > Define Capacity and sprint length
Expected Results
Teams should have the ability to include more than 1 capacity to manage Holidays and Leave
Actual Results
Teams offers to add only one Capacity and Sprint length c
...
Workaround
Required, if there is no workaround please state:
Currently there is no known workaround for this behavior. A workaround will be added here when available
That's an absolute must, there is no world in which the capacity of a team is the same in all the sprints. People take holidays, there are company/country holidays.