Issues being scheduled for a wrong person in Portfolio Plan

      There is a scheduling bug which results in issues being scheduled for a wrong person and surfaces under the following circumstances:

      • It concerns only sub-tasks having either an assignee in Portfolio or Jira assignees with a Jira assignee level above or equal sub-tasks.
      • There must be a certain number of possible member/sub-task assignments (which resource can be assigned to which sub-task).

      Workaround:
      Try reducing the possible assignments of sub-tasks. That means that if each of sub-tasks has either an assignee in Jira or an assignee in Portfolio, the problem will not appear.

            [JRACLOUD-88391] Issues being scheduled for a wrong person in Portfolio Plan

            Kate Durnell made changes -
            Component/s Original: Plan (Advanced Roadmaps) - Roadmap [ 61013 ]
            Component/s New: Plans - Timeline [ 77924 ]
            Key Original: JSWCLOUD-19307 New: JRACLOUD-88391
            Project Original: Jira Cloud [ 18511 ] New: Jira Platform Cloud [ 18514 ]
            Dylan made changes -
            Resolution New: Timed out [ 10 ]
            Status Original: Long Term Backlog [ 12073 ] New: Closed [ 6 ]
            Dylan made changes -
            Labels New: stale-bulk-close202006

            Dylan added a comment -

            Hi all,

            Thank you for raising this bug and bringing it to our attention.

            Within our company roadmap and work capacity, we try to address or review each bug request but admit that not each one will be resolved.

            To continue the culture of being honest and open, we are closing this bug to focus on our upcoming roadmap for all Jira users.

            Dylan added a comment - Hi all, Thank you for raising this bug and bringing it to our attention. Within our company roadmap and work capacity, we try to address or review each bug request but admit that not each one will be resolved. To continue the culture of being honest and open, we are closing this bug to focus on our upcoming roadmap for all Jira users.
            Owen made changes -
            Component/s New: Advanced Roadmaps [ 61013 ]
            Component/s Original: Advanced Roadmaps [ 61212 ]
            Key Original: JPOCLOUD-2071 New: JSWCLOUD-19307
            Project Original: Portfolio for JIRA Cloud [ 18510 ] New: Jira Software Cloud [ 18511 ]
            Owen made changes -
            Component/s New: Advanced Roadmaps [ 61212 ]
            Component/s Original: Scheduling [ 46297 ]
            Monique Khairuliana (Inactive) made changes -
            Workflow Original: JIRA Bug Workflow w Kanban v6 - Restricted [ 2679709 ] New: JAC Bug Workflow v3 [ 3439820 ]
            Status Original: Verified [ 10005 ] New: Long Term Backlog [ 12073 ]
            Albert Kavelar made changes -
            Status Original: Open [ 1 ] New: Verified [ 10005 ]
            Paulo F. (Inactive) made changes -
            Summary Original: Issues being scheduled for a wrong person in Plan New: Issues being scheduled for a wrong person in Portfolio Plan
            Paulo F. (Inactive) made changes -
            Description Original: There is a scheduling bug which results in issues being scheduled for a wrong person and surfaces under the following circumstances:

            * It concerns only sub-tasks having either an assignee in Portfolio or Jira assignees with a Jira assignee level above or equal sub-tasks.
            * There must be a certain number of possible member/sub-task assignments (which resource can be assigned to which sub-task).

            Workaround:
            To work around the problem we try to reducing the possible assignments of sub-tasks. That means that if each of sub-tasks has either an assignee in Jira or an assignee in Portfolio, the problem will not appear.
            New: There is a scheduling bug which results in issues being scheduled for a wrong person and surfaces under the following circumstances:

            * It concerns only sub-tasks having either an assignee in Portfolio or Jira assignees with a Jira assignee level above or equal sub-tasks.
            * There must be a certain number of possible member/sub-task assignments (which resource can be assigned to which sub-task).

            Workaround:
            Try reducing the possible assignments of sub-tasks. That means that if each of sub-tasks has either an assignee in Jira or an assignee in Portfolio, the problem will not appear.