Suggestion
-
Resolution: Unresolved
-
91
-
3
-
As described in the documentation Adding target dates, the live plans (or the old version of Portfolio) allows users to baseline a plan against target dates, and this feature isn't present in Advanced Roadmaps.
Suggested resolution
As an Advanced Roadmaps user, I want to be able to store an initial baseline to be able to compare at a future stage.
- mentioned in
-
Page Failed to load
[JRACLOUD-88013] As an Advanced Roadmaps user, I want to be able to baseline a plan against target dates