    • We collect Jira feedback from various sources, and we evaluate what we've collected when planning our product roadmap. To understand how this piece of feedback will be reviewed, see our Implementation of New Features Policy.

      Issue Summary

      When turning on roll-up for estimates in an AR plan, the roll up calculates the estimate and roll-up values against the parent. 

      In above screenshot; 

      Epic:

      • IOS-20 has 10 rolled up story points from stories and an estimate of 30 points against it. 
      • ARD-16 has 40 points estimated

      Initiative: PM-2 has rolled up story points value of 80. This is (10 + 30 + 40). We are doubling up on the estimate and roll up value from IOS-20. 

      Expected Results

      1. Option to have the story points value rolled up at only the story level to get an accurate representation of work estimated against the epic/initiative level. (preferred). 
      2. OR the story point roll up should be excluded automatically (calculation that removes from the estimate)  

      Actual Results

      Currently we are doubling up on the estimates as it calculates both the estimate field and the rolled up estimate when rolling up to parent. 
      

      Workaround

      Manually update the parent estimate to remove the values equivalent to the roll up or turn off roll up values feature. 