Details
-
Suggestion
-
Resolution: Unresolved
-
None
-
None
-
0
-
Description
Problem Definition
Currently, if an issue has more estimate than the remaining capacity, Portfolio will split the issue to multiple Sprints. Some users would like to turn off this feature and would like Portfolio to provide a hint to them that more resource is needed to complete the issue in a single Sprint.
Suggested Solution
Allow users to prevent issues from being split to multiple Sprint and force them to be included in specific Sprint. Also Portfolio should provide some hints to what can be done to ensure that the issues are completed in the Sprint.
Workaround
None.