Issues being scheduled for a wrong person in Portfolio Plan

      There is a scheduling bug which results in issues being scheduled for a wrong person and surfaces under the following circumstances:

      • It concerns only sub-tasks having either an assignee in Portfolio or Jira assignees with a Jira assignee level above or equal sub-tasks.
      • There must be a certain number of possible member/sub-task assignments (which resource can be assigned to which sub-task).

      Workaround:
      Try reducing the possible assignments of sub-tasks. That means that if each of sub-tasks has either an assignee in Jira or an assignee in Portfolio, the problem will not appear.

            [JRACLOUD-88391] Issues being scheduled for a wrong person in Portfolio Plan

            Dylan added a comment -

            Hi all,

            Thank you for raising this bug and bringing it to our attention.

            Within our company roadmap and work capacity, we try to address or review each bug request but admit that not each one will be resolved.

            To continue the culture of being honest and open, we are closing this bug to focus on our upcoming roadmap for all Jira users.

            Dylan added a comment - Hi all, Thank you for raising this bug and bringing it to our attention. Within our company roadmap and work capacity, we try to address or review each bug request but admit that not each one will be resolved. To continue the culture of being honest and open, we are closing this bug to focus on our upcoming roadmap for all Jira users.

              Unassigned Unassigned
              pferreira@atlassian.com Paulo F.
              Affected customers:
              4 This affects my team
              Watchers:
              5 Start watching this issue

                Created:
                Updated:
                Resolved: