Type:
Bug
-
Resolution: Support Request
-
Priority:
Medium
-
None
-
Affects Version/s: 6.6.0
-
Component/s: AgileBoard
-
Environment:
Self host at projects.mbww.com
-
6.06
Hi
I am a user of JIRA Agile. I have recently encountered an issue with JIRA Agile.
I created sprint 2 in project Zebra, and subsequently created sprint 2 in project Snapshot. The sprint id for both sprint are assigned to have the same id. I am expecting the two sprints to be not related to each other.
One issue I face is when I attempt to complete sprint 2 in Zebra, system complains that two of the issues in Snapshot project has not been completed.
Please check and let me know anything I can do to fix this?