Bug
-
Resolution: Unresolved
-
Low
-
None
-
TC-6.1.6
-
Severity 3 - Minor
-
Issue Summary
In Team Calendars list view, the Jira Sprint events only show on the first date and do not fill correctly as you navigate across to next day with the <> arrows. However they do show correctly in the dashboard calendar view.
Steps to Reproduce
Discovered in TC 6.1.6 but affects previous versions.
- Step 1 - Create a Jira sprint event that spans more than one day.
- Step 2 - Display the Jira sprint event on your team calendar.
Expected Results
The Jira sprint event should show up on each day it occurs in the list view
Actual Results
The Sprint event only shows up on the first day it's loaded in listview (however it shows correctly on the dashboard over several days)
Workaround
Currently there is no known workaround. View sprint events in week or month view for an accurate representation of dates.
- is related to
-
CONFSERVER-50018 List View does not show the last day of the event
-
- Gathering Impact
-