Uploaded image for project: 'Confluence Cloud'
  1. Confluence Cloud
  2. CONFCLOUD-70623

Task is not removed from the task report macro if the page in restored or task is removed from original page

    XMLWordPrintable

Details

    • Bug
    • Resolution: Cannot Reproduce
    • High
    • Macros - Task Report
    • None

    Description

      Summary

      The task is not removed from the task report macro if the page is restored in a previous version on which task doesn't exist.
      And when we try to mark this task complete it throws an error "Oops! Your task change couldn't be saved.
      There could be a few reasons for this. Dismiss"

      Steps to Reproduce

      1. Create a task on any page
      2. Publish the page (The task will now show up in the macro)
      3. Restore an older version the page on which the task was created (The task will still show up in the macro; when trying to mark the task as completed, the error occurs)
      or
      1. Create a task on any page
      2. check the task in the task report macro
      3. Remove the task from the original page
      4. Task still shows in the task report macro and try to complete the task.

      Expected Results

      The task should be removed from the task report macro.

      Actual Results

      The task is still showing on the task report macro and it can't be marked as complete.

      Workaround

      Currently, there is no known workaround for this behavior. A workaround will be added here when available

      Attachments

        Activity

          People

            Unassigned Unassigned
            nghuraiya@atlassian.com Neha Ghuraiya
            Votes:
            5 Vote for this issue
            Watchers:
            14 Start watching this issue

            Dates

              Created:
              Updated:
              Resolved: