Uploaded image for project: 'Bamboo Data Center'
  1. Bamboo Data Center
  2. BAM-3224

SvnRepository unit tests shall be independent of network infrastructure

    XMLWordPrintable

Details

    • Suggestion
    • Resolution: Fixed
    • 2.1.5
    • None
    • None
    • Our product teams collect and evaluate feedback from a number of different sources. To learn more about how we use customer feedback in the planning process, check out our new feature policy.

    Attachments

      Activity

        People

          Unassigned Unassigned
          Anonymous Anonymous
          Votes:
          0 Vote for this issue
          Watchers:
          0 Start watching this issue

          Dates

            Created:
            Updated:
            Resolved:

            Time Tracking

              Estimated:
              Original Estimate - 10h Original Estimate - 10h
              10h
              Remaining:
              Time Spent - 13.25h Remaining Estimate - 2.75h
              2.75h
              Logged:
              Time Spent - 13.25h Remaining Estimate - 2.75h
              13.25h