Suggestion
-
Resolution: Fixed
-
None
Looking at AnthillPro, they have the concept of a quite period on commits. User sets a value (say 5 minutes) for the quiet period. Build is triggered when there are commits AND a quiet period of time has passed with NO commits. This allows for a bunch of commits to be done before build is kicked of. For instance, 2 or more developers coordinating their commits. Also covers the case when a single developer "forgets" submitting something and needs to correct it quickly.
- is duplicated by
-
BAM-926 An option to delay building after checkout detected for SVN
- Closed
-
BAM-2406 Allow for a repository "cool down" period before executing a build
- Closed
- is related to
-
BAM-926 An option to delay building after checkout detected for SVN
- Closed
- relates to
-
BAM-7410 Mercurial quiet period