Issue Summary
When syncing a Jira epic and project from an Atlas project, it only populates the 'Start Date' from the project, and not from the Jira epic.
But when syncing from Jira, it shows both start dates from the Jira epic and project.
Steps to Reproduce
- Open a project
- Go to the 'Where is work tracked?' section and click on the + button
- Add a Jira epic link
- Click on the 'Sync with Jira' button
Expected Results
- Start date options include both start dates from the Jira epic and Atlas project, so the user can select which start date to sync.
Actual Results
- Start date only shows the start date from the Atlas project with no option to select the Jira epic start date.
Workaround
Go to the Jira epic and link and sync with the project from the 'Project overview' section by clicking on the 'Link a project overview' button.