When push update to project, Epic-Story linkage is not updated based on Portfolio Plan

XMLWordPrintable

      NOTE: This suggestion is for JIRA Portfolio Cloud. Using JIRA Portfolio Server? See the corresponding suggestion.

      I imported all epics and stories from JIRA.

      When push update via Plan > Apply updates to project/s, despite all items under Update linked elements are selected, the Epic-Story links are not updated.

      Steps to reproduce:

      • Import Story and Epics from JIRA
      • Create new Epic and corresponding JIRA Epic using Portfolio
      • Move existing Story under new Epic using Portfolio
      • Click Plan > Apply updates to projects/s

      Current Behaviour

      • New JIRA Epic does not link with the JIRA Story
      • The JIRA Story still links with original JIRA Epic

      Expected Behaviour

      • The JIRA Story should now linked with the new JIRA Epic created from Portfolio

      (We are using Atlassian Cloud)